Extending time to complete drain construction.

Citation: N.D. Admin. Code § 89-02-01-09.12

Section: 89-02-01-09.12

89-02-01-09.12. Extending time to complete drain construction. The permit recipient may make a written request to the board for a one-year extension to the time to complete the drain's construction. Only two extensions may be granted. All requests for extensions must be made at least sixty days before the expiration date and must specifically state why construction has not been completed. If the request is for an extension relating to a permit of statewide or interdistrict significance, the extension must be submitted to and approved by both the director and the board. History: Effective February 1, 1997; amended effective April 1, 2004; January 1, 2015; January 1, 2023; April 1, 2026. General Authority: NDCC 61-03-13 Law Implemented: NDCC 61-32-03